What to settle before the first OEM order

MOQ, tooling ownership, certification route and artwork approval decide whether a first order ships on time. This is the order we recommend.

What to settle before the first OEM order

Start with the destination market, not the product. CE and RoHS for the EU, FCC for the US, PSE for Japan and KC for Korea imply different components, labels and test reports. Changing the market after tooling is where schedules break.

Then fix the commercial frame in one page: MOQ per model and per colour, tooling cost and who owns the mould, sample approval rounds, Incoterms and payment terms. Writing it down before the first sample prevents most disputes later.

Artwork and barcodes come next, then certification samples, then mass production. A realistic first run allows two sample rounds and four to six weeks for testing before the line starts.